Make to stock (MTS) means you build finished goods before a customer asks, then sell from the shelf. Make to order (MTO) means you start production only after a customer order is confirmed. Build ahead when the item is standard, sells steadily, and customers expect delivery in days. Build to order when the item is custom, demand is uneven, or stock would sit unsold. Most small Indian factories end up running both, item by item.

In this guide

  1. What MTS and MTO mean on the shop floor
  2. Comparison table
  3. Signs to build ahead, and signs to wait
  4. Running a hybrid
  5. What to track for each
  6. Common mistakes
  7. FAQ

What MTS and MTO mean on the shop floor

The two terms sound academic, but the difference shows up in one question: who is the production order for, a customer or the shelf?

Make to stock examples:

  • A fastener or fittings unit that runs standard sizes and sells from the godown to dealers.
  • A packaging unit that keeps common carton or pouch sizes ready because repeat buyers reorder at short notice.
  • Any standard SKU with a catalogue, a price list, and a customer who wants it this week.

Here the production order is raised by a stock decision: the finished-goods level has dropped to your reorder level, so you make a batch.

Make to order examples:

  • A custom fabrication shop building a frame, tank, or structure to a customer drawing. Nobody else can use it.
  • A job shop machining parts to a customer specification.
  • A garment unit making a customer-spec order by size, say 200 pieces split across S, M, L and XL against a buyer's size ratio. Stocking those pieces ahead would be a bet on a buyer you do not have yet.

Here the production order is raised by a confirmed sales order, with the quantity, date, and specification coming from the customer. If you are unsure how a production order differs from the stage-level tasks under it, see production order vs work order.

Make to stock vs make to order at a glance

Make to stockMake to order
Triggered byReorder level or forecastConfirmed sales order
Cash tied up in stockHigh: finished goods sit on the shelfLow: you build once the order is firm
Lead time to the customerShort: ship from stockLonger: customer waits for production
Forecast riskHigh: you are guessing demandLow: demand is a real order
Dead stock riskReal, especially on slow SKUsMinimal for finished goods
Planning effortSteady: reorder levels and batch sizesHeavier per order: dates, material, and capacity each time
Best forStandard, repeat, fast-moving itemsCustom, low-volume, or lumpy-demand items

Neither column is free. Make to stock moves the cost into working capital and forecast error. Make to order moves it into waiting time and planning work on every job. If cash is the tighter constraint, read working capital in manufacturing before deciding what to build ahead.

Signs to build ahead and signs to wait

Build ahead (make to stock) when:

  • The item is standard and the specification never changes between customers.
  • You see repeat orders at a steady pace, so last quarter's sales are a fair guide to the next.
  • Customers expect delivery faster than your production plus material lead time.
  • Setup or changeover is expensive, so running a larger batch is cheaper per piece.
  • The item does not spoil, go out of fashion, or become obsolete quickly.

Wait for the order (make to order) when:

  • The product carries a customer's drawing, specification, or size breakup.
  • Demand is lumpy: nothing for a month, then one big order.
  • The item is expensive, so a few unsold pieces hurt.
  • Raw material is costly or slow to source, and you cannot afford to lock it into finished goods.
  • You have been left with stock of the same item before and it took months to clear.

If an item fits neither list cleanly, treat it as a hybrid candidate, covered next.

Running a hybrid: stock the common parts, finish to order

Most small factories do not choose one mode for the whole shop. They split the process at a sensible point.

1. Stock raw material that many products share. Common sheet, bar, fabric, or packaging material can be held at a level you set. This is the cheapest buffer, because material has more than one possible use.

2. Stock common sub-assemblies. If ten finished variants all use the same machined body or the same cut-and-stitched panel set, build those ahead and keep them as semi-finished stock. When an order lands, only the final operations remain.

3. Finish to order. The customer-specific steps, such as final assembly, custom size, marking, or packing to the buyer's requirement, wait for a confirmed sales order. Lead time drops because most of the work is already done, without finished-goods stock that may never sell.

4. Set reorder levels for fast movers only. For your handful of standard items that sell every week, set a reorder level and a standard batch quantity. When finished stock falls to that level, raise a production order. Do not set levels for every SKU; that is how stock builds on items nobody asked for.

Your bill of materials is what makes this possible, because it tells you which parts are common across products. See what a bill of materials is if you have not set yours up.

What to track for each

The two modes need different records, and a hybrid needs both.

For make to order:

  • Sales order to production order. The confirmed item, quantity, and date should flow into the production order, not be retyped. Dates matter more here, because the customer is waiting. See how sales orders stay linked to production and dispatch.
  • Material for that order. Check required material against what is free, and flag shortages before the job starts. Production planning and MRP covers how requirements are calculated from the BOM.

For make to stock:

  • Finished-goods stock. The on-hand count for each standard item, with a reorder level you act on.
  • Production orders raised by the reorder level, with a standard batch size, not an ad hoc number.

For both:

  • Reserved vs free stock. Stock reserved for a confirmed order is not available to promise elsewhere. If you only track total on-hand, you will sell the same pieces twice. Inventory management covers reservations and reorder alerts.
  • Work in progress. Half-finished jobs hold material and cash. Track them by stage, as explained in how to track WIP inventory.
  • Dispatch. Record what actually left against which order, including partial shipments, so finished stock and order status both stay true.

In FactoStack, these records sit together: a sales order carries into production, production reserves material, finished goods are received into stock, and dispatch closes the order. For the MRP side in more depth, read MRP for small manufacturers in India.

Common mistakes

Building stock from gut feel. "This one always sells" is how a shelf fills with last year's favourite. Use actual sales history, a reorder level, and a fixed batch size, and review them.

No reservation against orders. Without reservation, stock built for a confirmed order gets sold or issued elsewhere. The order then slips, and nobody knows why until the customer calls.

Excel stock that never matches the godown. If receipts, issues, and dispatches are keyed in late or by different people, the sheet drifts from reality. A reorder level against a wrong number is worse than no reorder level.

Treating every item the same. Applying make to stock to custom work ties up cash. Applying make to order to a fast standard item loses sales to a competitor who ships from stock.

Ignoring cost. Stock you built carries material, labour, and overhead. Before you commit to a batch, check what a unit costs with the production cost calculator.

Production Planning & MRP

Turn sales orders into production orders, check material before the job starts, and keep finished-goods stock and reservations in one place.

Frequently Asked Questions

What is the difference between make to stock and make to order?

Make to stock builds finished goods ahead of demand and sells from the shelf. Make to order starts production only after a customer order is confirmed.

Which is better for a small factory?

Neither everywhere. Standard, steady items suit make to stock; custom or lumpy items suit make to order. Most small factories run both, decided item by item.

What is a hybrid approach?

Stock raw material and common sub-assemblies ahead, then finish the product when a sales order arrives. Lead time drops without building finished goods that may not sell.

How do I stop stock built for one order being used for another?

Reserve it against the sales order. Reserved stock stays physically on the shelf but is no longer free to promise elsewhere.

Do I need software to run both?

A disciplined sheet can start you off. It tends to break once several orders compete for the same material and reserved and free stock must be kept apart.

Run Both Modes in FactoStack

Factory OS is ₹2,999/month. It links sales orders, production orders, inventory with reservations and reorder alerts, and dispatch for Indian factories.

Sudharsan GS

Written by

Sudharsan GS

Building FactoStack with Indian MSME manufacturers across inventory, production, dispatch, GST, and Tally workflows.

Let's take your plant live

On-prem or cloud, around your process. Go-live is scoped on a call.

Book a go-live call